GAO: $12.8B Navy Carrier Project Weighed Down With Problems

Thursday, 27 June 2013 04:07 PM EDT

The U.S. Navy should delay the award of a multibillion-dollar contract to Huntington Ingalls Industries Inc. to build the second aircraft carrier in a new class as the first one faces failings from its radar to the gear that launches planes, congressional investigators said.

“Technical, design and construction challenges” with the first carrier, the USS Gerald R. Ford, have caused “significant cost increases and reduce the likelihood that a fully functional ship will be delivered on time,” the Government Accountability Office said in a draft report obtained by Bloomberg News.

The Ford, already the most expensive warship ever built, is projected to cost $12.8 billion, 22 percent more than estimated five years ago. The report raises questions about the future of U.S. seapower in a time of reduced defense budgets and about whether new carriers are affordable as they assume greater importance in the Pentagon’s strategy to project U.S. power in the Asia-Pacific region.

Delays and “reliability deficiencies” with the flattop’s new dual-mission radar, electromagnetic launch system and arresting gear for aircraft mean that the Ford “will likely face operational limitations that extend past commissioning” in March 2016 and “into initial deployments,” the agency said.

The GAO, the investigative arm of Congress, said that’s reason enough to delay the contract that’s scheduled to be issued this year for the second ship, the USS John F. Kennedy.

‘Repeating Mistakes’

“It will be important to avoid repeating mistakes” in the contract for the Kennedy, the GAO said. “Staying within budget” will require the Navy to reduce “significant risk mainly by completing land-based testing for critical technologies before negotiating a contract” with Newport News, Virginia-based Huntington Ingalls.

Beci Brenton, a company spokeswoman, said in a telephone interview that “it would not be appropriate to comment on a draft report.”

Naval Sea Systems Command spokeswoman Colleen O’Rourke said the command also wouldn’t comment.

“As the Navy is currently working with the GAO on this report, it would be inappropriate to comment on any draft findings at this time,” she said in an e-mail. “When the report is finalized, it will include Navy comments.”

Huntington Ingalls rose 2.4 percent to $56.64 in New York at 3:20 p.m. after rising 31 percent this year.

The Navy is grappling with how to pay for a shipbuilding plan that anticipates $43 billion for three carriers in the Ford class, as well as $34 billion for 52 Littoral Combat Ships and a 12-vessel nuclear submarine fleet to replace the Ohio-class submarine.

Estimate ‘Optimistic’

While the GAO said that the Navy and Huntington Ingalls are taking steps to control costs for the Ford, most increases occur after a vessel is 60 percent complete and key systems are installed and integrated. The Ford is now 56 percent complete.

Even the current $12.8 billion estimate is “optimistic because it assumes the shipbuilder will maintain its current level of performance throughout the remainder of construction,” the GAO said.

The Pentagon’s independent cost-estimating office, the Congressional Budget Office and a Navy-commissioned panel project final costs as high as $14.2 billion, the GAO said.

The draft report also raises questions about how many aircraft carriers the nation will have ready this decade. Congress has given the service temporary relief from the requirement to have 11 fully capable aircraft carriers. There are now 10 after deactivation of the USS Enterprise, and the Ford is supposed to bring that back to 11 by March 2016.

‘Reliability Shortfalls’

“As it now stands, the Navy will not be positioned to deliver a fully capable ship at the time,” the GAO said.

“Reliability shortfalls facing key Ford-class systems cloud the Navy’s ability to forecast when, or if” the carrier will meet the aircraft sortie rates and reduced manning requirements that distinguish it from the older Nimitz class, the GAO said.

O’Rourke, the Naval Sea Systems Command spokeswoman, wouldn’t comment on the specific value of the potential detailed design and construction contract to Huntington Ingalls for the Kennedy that the GAO said is due in September.

Cost Breakdown

The largest share of the cost increase for the Ford, 38 percent, stemmed from technologies delivered by the Navy, including the radar, launch system and arresting gear, according to the GAO.

The electromagentic launch system made by San Diego-based General Atomics has increased to $742.6 million, up 134 percent since 2008, the GAO said. The cost of arresting gear also made by the company increased 125 percent to $169 million.

Raytheon Co.’s dual-band radar has increased 140 percent to $484 million, according to data cited by the GAO. Twenty-seven percent of the cost growth was pegged to shipbuilder design issues and another 27 percent to construction, both attributed to Huntington Ingalls.

Huntington Ingalls is building the Ford under a $4.9 billion detailed design contract that covers the shipbuilder’s portion of constructing the vessel. It doesn’t cover other costs, such as the nuclear reactor to power the ship and other government-furnished equipment.

The GAO said its analysis indicates that Huntington Ingalls “was forecasting an overrun at contract completion of over $913 million” that it said stemmed from “the shipbuilder not accomplishing work as planned.”

Huntington’s Brenton said in an e-mail in May that, “as the first new design carrier beginning construction in more than 40 years,” the Ford “is designed to provide increased capability and reduced total ownership cost by about $4 billion compared to Nimitz-class carriers.”

“For this first-of-class ship, construction commenced in parallel with design completion based on earlier decisions at Department of Defense,” she said. “Ongoing design during the construction process caused delay and inefficiencies in procurement, manufacturing, and assembly.”


© Copyright 2025 Bloomberg News. All rights reserved.

Sign up for Newsmax’s Daily Newsletter

Receive breaking news and original analysis - sent right to your inbox.

(Optional for Local News)
Privacy: We never share your email address.

Newsfront
The U.S. Navy should delay the award of a multibillion-dollar contract to Huntington Ingalls Industries Inc. to build the second aircraft carrier in a new class as the first one faces failings from its radar to the gear that launches planes.
navy,aircraft,carrier,gao
929
2013-07-27
Thursday, 27 June 2013 04:07 PM
Newsmax Media, Inc.
Join the Newsmax Community
Read and Post Comments
Please review Community Guidelines before posting a comment.
 

Interest-Based Advertising | Do not sell or share my personal information

Newsmax, Moneynews, Newsmax Health, and Independent. American. are registered trademarks of Newsmax Media, Inc. Newsmax TV, and Newsmax World are trademarks of Newsmax Media, Inc.

NEWSMAX.COM
America's News Page
© 2025 Newsmax Media, Inc.
All Rights Reserved
Download the Newsmax App
NEWSMAX.COM
America's News Page
© 2025 Newsmax Media, Inc.
All Rights Reserved